PROJECT UPDATE - August 11, 2025Uranium Avenue has been paved and is now open to traffic.
100 East from 300 South to Uranium is closed as crews finish preparation
for road resurfacing. Grand Avenue access to the middle school is closed for now, but will be open whenever the 100 East paving phase allows.
To access Margaret L. Hopkin Middle School, use Uranium Ave. to the school parking lot. Drivers can exit via Grand Avenue when access across 100 East is open, or loop back through the parking lot to exit onto Uranium. School bus drop-off will be near the tennis courts as usual.
For students walking to school, a temporary route has been created east of the Bark Park leading from 300 South to the middle school property.
Follow project progress at our community engagement website https://engagemoab.com/100-east-improvements
PROJECT UPDATE - August 5, 2025
Uranium is paved and will reopen after concrete work in some areas is completed. Uranium is expected to reopen Aug. 8 or early in the week of Aug.

11.
100 East access is closed completely except for access to Margaret L. Hopkin Middle School via Grand Avenue, crossing 100 East. That access will change when Uranium is reopened and paving on 100 East begins.
Access to the middle school for student drop-offs will be via Uranium and across to the school parking lot as normal, exiting via Grand Avenue. When Grand Avenue access is closed at 100 East for construction, drivers dropping students off will loop back through the parking lot to exit onto Uranium. The school bus drop-off will be near the tennis courts as usual.
PROJECT UPDATE - July 16, 2025
The installation of curb and gutter along Uranium Avenue has been completed. In preparation for paving, roadbase installation is nearly finished along Uranium Avenue. The water main along 100 East has been installed and will undergo water quality testing soon.
PROJECT UPDATE - Week of July 7, 2025
The removal of the existing concrete, asphalt, and subgrade will commence along 100 East, north of Grand Avenue. The installation of electrical conduit will be completed along Uranium Avenue and will subsequently begin along 100 East.
PROJECT UPDATE - July 3, 2025
Uranium Avenue remains closed to through traffic.
100 East is now closed south of Grand Avenue.
Through July 18:
Vehicle & pedestrian traffic remains closed along Uranium 100 East is closed south of Grand Ave. Access to Margaret L. Hopkin Middle School is open on 100 East at the Grand Avenue intersection.
Detours are posted.
Access City Market via Grand Avenue or Main Street.
PROJECT UPDATE - June 16, 2025
Construction began on the Uranium Ave./100 East Road Improvement project on Tuesday, June 17.
Phase 1
Uranium Avenue will be closed to through traffic while the existing pavement is removed, underground infrastructure work is done, and new pavement is installed. Detours will be posted.
Phase 1 Anticipated Timeline
Contractor expects work on Uranium Avenue to be completed by the first two weeks of August.
Detours during Uranium Ave. construction
Please use 100 East, Grand Avenue, or Main Street to access City Market while Uranium is under construction.
Phase 2
100 East repaving and underground infrastructure work.
Detours during 100 East construction
Access to City Market will be via Grand Avenue or Main Street.
We appreciate your patience during this much-needed improvement project.
Thank you!
Project Description
The scope of the 100 East & Uranium Avenue project includes full-depth roadway reconstruction, street lighting, utility upgrades, and landscaping. Final improvements may include:
Additional enhancements include the widening of the shared use path along the eastern side of 100 East, and the construction of a new shared use path along the northern side of Uranium Avenue. Parallel parking stalls will also be added on the eastern side of 100 East.
The contractor will take measures to minimize dust and noise during construction. However, for the duration of the roadway reconstruction, it is recommended that City Market be accessed via Highway 191 / South Main Street or Grand Avenue.
Barring unforeseen delays, the 100 East & Uranium Avenue reconstruction is expected to be completed before the start of the 2025–2026 school year.
Contractor: Kilgore Companies, dba LeGrand Johnson
Bid Cost: $2,539,055.50
Streets Included In This Project: 100 East; Uranium Ave.

PROJECT UPDATE - August 11, 2025Uranium Avenue has been paved and is now open to traffic.
100 East from 300 South to Uranium is closed as crews finish preparation
for road resurfacing. Grand Avenue access to the middle school is closed for now, but will be open whenever the 100 East paving phase allows.
To access Margaret L. Hopkin Middle School, use Uranium Ave. to the school parking lot. Drivers can exit via Grand Avenue when access across 100 East is open, or loop back through the parking lot to exit onto Uranium. School bus drop-off will be near the tennis courts as usual.
For students walking to school, a temporary route has been created east of the Bark Park leading from 300 South to the middle school property.
Follow project progress at our community engagement website https://engagemoab.com/100-east-improvements
PROJECT UPDATE - August 5, 2025
Uranium is paved and will reopen after concrete work in some areas is completed. Uranium is expected to reopen Aug. 8 or early in the week of Aug.

11.
100 East access is closed completely except for access to Margaret L. Hopkin Middle School via Grand Avenue, crossing 100 East. That access will change when Uranium is reopened and paving on 100 East begins.
Access to the middle school for student drop-offs will be via Uranium and across to the school parking lot as normal, exiting via Grand Avenue. When Grand Avenue access is closed at 100 East for construction, drivers dropping students off will loop back through the parking lot to exit onto Uranium. The school bus drop-off will be near the tennis courts as usual.
PROJECT UPDATE - July 16, 2025
The installation of curb and gutter along Uranium Avenue has been completed. In preparation for paving, roadbase installation is nearly finished along Uranium Avenue. The water main along 100 East has been installed and will undergo water quality testing soon.
PROJECT UPDATE - Week of July 7, 2025
The removal of the existing concrete, asphalt, and subgrade will commence along 100 East, north of Grand Avenue. The installation of electrical conduit will be completed along Uranium Avenue and will subsequently begin along 100 East.
PROJECT UPDATE - July 3, 2025
Uranium Avenue remains closed to through traffic.
100 East is now closed south of Grand Avenue.
Through July 18:
Vehicle & pedestrian traffic remains closed along Uranium 100 East is closed south of Grand Ave. Access to Margaret L. Hopkin Middle School is open on 100 East at the Grand Avenue intersection.
Detours are posted.
Access City Market via Grand Avenue or Main Street.
PROJECT UPDATE - June 16, 2025
Construction began on the Uranium Ave./100 East Road Improvement project on Tuesday, June 17.
Phase 1
Uranium Avenue will be closed to through traffic while the existing pavement is removed, underground infrastructure work is done, and new pavement is installed. Detours will be posted.
Phase 1 Anticipated Timeline
Contractor expects work on Uranium Avenue to be completed by the first two weeks of August.
Detours during Uranium Ave. construction
Please use 100 East, Grand Avenue, or Main Street to access City Market while Uranium is under construction.
Phase 2
100 East repaving and underground infrastructure work.
Detours during 100 East construction
Access to City Market will be via Grand Avenue or Main Street.
We appreciate your patience during this much-needed improvement project.
Thank you!
Project Description
The scope of the 100 East & Uranium Avenue project includes full-depth roadway reconstruction, street lighting, utility upgrades, and landscaping. Final improvements may include:
Additional enhancements include the widening of the shared use path along the eastern side of 100 East, and the construction of a new shared use path along the northern side of Uranium Avenue. Parallel parking stalls will also be added on the eastern side of 100 East.
The contractor will take measures to minimize dust and noise during construction. However, for the duration of the roadway reconstruction, it is recommended that City Market be accessed via Highway 191 / South Main Street or Grand Avenue.
Barring unforeseen delays, the 100 East & Uranium Avenue reconstruction is expected to be completed before the start of the 2025–2026 school year.
Contractor: Kilgore Companies, dba LeGrand Johnson
Bid Cost: $2,539,055.50
Streets Included In This Project: 100 East; Uranium Ave.