100 East / Uranium Avenue Reconstruction

Share 100 East / Uranium Avenue Reconstruction on Facebook Share 100 East / Uranium Avenue Reconstruction on Twitter Share 100 East / Uranium Avenue Reconstruction on Linkedin Email 100 East / Uranium Avenue Reconstruction link

PROJECT UPDATE - June 16, 2025
Construction began on the Uranium Ave./100 East Road Improvement project on Tuesday, June 17.


Phase 1
Uranium Avenue will be closed to through traffic while the existing pavement is removed, underground infrastructure work is done, and new pavement is installed. Detours will be posted.


Phase 1 Anticipated Timeline
Contractor expects work on Uranium Avenue to be completed by the first two weeks of August.

Detours during Uranium Ave. construction
Please use 100 East, Grand Avenue, or Main Street to access City Market while Uranium is under construction.

Phase 2
100 East repaving and underground infrastructure work.

Detours during 100 East construction
Access to City Market will be via Grand Avenue or Main Street.

We appreciate your patience during this much-needed improvement project.

Thank you!


Project Description

The scope of the 100 East & Uranium Avenue project includes full-depth roadway reconstruction, street lighting, utility upgrades, and landscaping. Final improvements may include:

  • Roadway reconstruction

  • Curb and gutter installation

  • Concrete flatwork

  • Drainage improvements

  • Street lighting

  • Trenching/boring for conduit

  • Waterline installation

  • Landscaping

Additional enhancements include the widening of the shared use path along the eastern side of 100 East, and the construction of a new shared use path along the northern side of Uranium Avenue. Parallel parking stalls will also be added on the eastern side of 100 East.

The contractor will take measures to minimize dust and noise during construction. However, for the duration of the roadway reconstruction, it is recommended that City Market be accessed via Highway 191 / South Main Street or Grand Avenue.

Barring unforeseen delays, the 100 East & Uranium Avenue reconstruction is expected to be completed before the start of the 2025–2026 school year.

Contractor: Kilgore Companies, dba LeGrand Johnson

Bid Cost: $2,539,055.50


Streets Included In This Project: 100 East; Uranium Ave.



PROJECT UPDATE - June 16, 2025
Construction began on the Uranium Ave./100 East Road Improvement project on Tuesday, June 17.


Phase 1
Uranium Avenue will be closed to through traffic while the existing pavement is removed, underground infrastructure work is done, and new pavement is installed. Detours will be posted.


Phase 1 Anticipated Timeline
Contractor expects work on Uranium Avenue to be completed by the first two weeks of August.

Detours during Uranium Ave. construction
Please use 100 East, Grand Avenue, or Main Street to access City Market while Uranium is under construction.

Phase 2
100 East repaving and underground infrastructure work.

Detours during 100 East construction
Access to City Market will be via Grand Avenue or Main Street.

We appreciate your patience during this much-needed improvement project.

Thank you!


Project Description

The scope of the 100 East & Uranium Avenue project includes full-depth roadway reconstruction, street lighting, utility upgrades, and landscaping. Final improvements may include:

  • Roadway reconstruction

  • Curb and gutter installation

  • Concrete flatwork

  • Drainage improvements

  • Street lighting

  • Trenching/boring for conduit

  • Waterline installation

  • Landscaping

Additional enhancements include the widening of the shared use path along the eastern side of 100 East, and the construction of a new shared use path along the northern side of Uranium Avenue. Parallel parking stalls will also be added on the eastern side of 100 East.

The contractor will take measures to minimize dust and noise during construction. However, for the duration of the roadway reconstruction, it is recommended that City Market be accessed via Highway 191 / South Main Street or Grand Avenue.

Barring unforeseen delays, the 100 East & Uranium Avenue reconstruction is expected to be completed before the start of the 2025–2026 school year.

Contractor: Kilgore Companies, dba LeGrand Johnson

Bid Cost: $2,539,055.50


Streets Included In This Project: 100 East; Uranium Ave.


Ask a question about this project

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
Page last updated: 18 Jun 2025, 03:38 PM