Downtown Dispersed Parking

Share Downtown Dispersed Parking on Facebook Share Downtown Dispersed Parking on Twitter Share Downtown Dispersed Parking on Linkedin Email Downtown Dispersed Parking link
A map showing the parking design for multiple streets in Downtown Moab


The City of Moab began construction on the Downtown Dispersed project on Monday, February 12, 2024.

Project Activities:*


  • Crews continue placing concrete on the west side at 100 North and 200 North at the islands and waterways. Crews have begun work on the island at the corner of 100 North and Main Street. Lanes are narrowed and motorists are advised to drive with caution.
  • Crews have begun work on a waterline through the north side of the 100 East and 100 North intersection. During this work, the north side of the intersection will be closed a half at a time to get the line through the intersection. This work will take approximately one week. Motorists are advised to use alternate routes to avoid any delays.
  • Landscaping crews will be onsite for the next few weeks as they continue working on the islands. Motorists may experience intermittent parking limitations as the landscaping crew works.
  • As construction progresses, area businesses and residents should be prepared at times for one-way traffic, access interruptions, no on-street parking, and traffic delays while work is occurring.



Crews forming new island at 100 North and Main Street

Curb and gutter at 100 North and 100 East

Project Description

The City of Moab has redesigned parking downtown to add 193 additional parking stalls, making more efficient use of the available space and helping to reduce congestion. The project will also improve options for visitors to walk to downtown businesses, provide more ADA parking options, and enhance the look and feel of downtown. This project is funded with recreation hotspot funding provided by the Utah Department of Transportation (UDOT) to address congestion and parking issues in downtown Moab.

The project will add the following improvements:

  • Center-angle parking on Center Street between Main Street and 200 East, and on 100 East between 100 North and Center Street.

  • Shoulder angle and parallel parking on the other blocks. 

  • ADA parking stalls in several locations.

  • Improved crosswalks and bulb-outs (extended curbs to make crossing shorter and safer) at multiple intersections.

  • Center and shoulder islands to assist in traffic calming.

  • Aesthetic improvements including xeriscape elements, plants, trees, shade structures, benches, bicycle racks, and trash and recycling receptacles in the downtown core.

  • Improved lighting.

  • Pavement resurfacing and striping.

Project Schedule

Construction is anticipated to begin on February 12, 2024 and extend into the summer. Crews expect to begin work on Center Street between Main Street and 200 East and then on 100 East between 100 North and 100 South* while traffic and visitor numbers are lower.

Work is anticipated to begin with underground utility relocation or replacement, then concrete installation, followed by pavement restoration and striping. Landscape restoration, planting, and installation of other amenities (where applicable) are the final items.

*Construction phasing and schedules are subject to change

Anticipated Impacts

Construction will impact adjacent residents and businesses, as well as the traveling public. The work will be phased to reduce those impacts where possible. Crews will work to maintain traffic whenever possible, however, you can expect traffic to be restricted to one-lane with flaggers at times.

Intermittent access closures may occur while utility or concrete work is underway. A safe walking route will be provided on one side of the block at a time.

Project Background and History

In 2019, the Moab City Council approved the Moab Parking Management Study to guide how parking concerns are addressed in the downtown area. Parking availability, relocation of parking following the recent U.S. 191 widening project, addressing the number of oversized vehicles and trailers, and safety considerations for vehicles, bicycles and pedestrians were all considered. In 2020, it was agreed that the Utah Department of Transportation (UDOT) recreation hotspot funding would be used to address congestion by dispersing parking around the downtown area to increase overall parking by 193 stalls.

In 2022, the City of Moab team held two workshops for area business owners, residents, and property owners, and a public open house to gather input on the proposed design. The final design has incorporated much of this public feedback to help address some issues and concerns the public shared with the team.

Moab has a Public Information Team for the Downtown Dispersed Parking Project. We are available to address questions or concerns specific to this project. Let us know how we can help!

Email: downtownparking@moabcity.org

Call: 888-670-0245


The City of Moab began construction on the Downtown Dispersed project on Monday, February 12, 2024.

Project Activities:*


  • Crews continue placing concrete on the west side at 100 North and 200 North at the islands and waterways. Crews have begun work on the island at the corner of 100 North and Main Street. Lanes are narrowed and motorists are advised to drive with caution.
  • Crews have begun work on a waterline through the north side of the 100 East and 100 North intersection. During this work, the north side of the intersection will be closed a half at a time to get the line through the intersection. This work will take approximately one week. Motorists are advised to use alternate routes to avoid any delays.
  • Landscaping crews will be onsite for the next few weeks as they continue working on the islands. Motorists may experience intermittent parking limitations as the landscaping crew works.
  • As construction progresses, area businesses and residents should be prepared at times for one-way traffic, access interruptions, no on-street parking, and traffic delays while work is occurring.



Crews forming new island at 100 North and Main Street

Curb and gutter at 100 North and 100 East

Project Description

The City of Moab has redesigned parking downtown to add 193 additional parking stalls, making more efficient use of the available space and helping to reduce congestion. The project will also improve options for visitors to walk to downtown businesses, provide more ADA parking options, and enhance the look and feel of downtown. This project is funded with recreation hotspot funding provided by the Utah Department of Transportation (UDOT) to address congestion and parking issues in downtown Moab.

The project will add the following improvements:

  • Center-angle parking on Center Street between Main Street and 200 East, and on 100 East between 100 North and Center Street.

  • Shoulder angle and parallel parking on the other blocks. 

  • ADA parking stalls in several locations.

  • Improved crosswalks and bulb-outs (extended curbs to make crossing shorter and safer) at multiple intersections.

  • Center and shoulder islands to assist in traffic calming.

  • Aesthetic improvements including xeriscape elements, plants, trees, shade structures, benches, bicycle racks, and trash and recycling receptacles in the downtown core.

  • Improved lighting.

  • Pavement resurfacing and striping.

Project Schedule

Construction is anticipated to begin on February 12, 2024 and extend into the summer. Crews expect to begin work on Center Street between Main Street and 200 East and then on 100 East between 100 North and 100 South* while traffic and visitor numbers are lower.

Work is anticipated to begin with underground utility relocation or replacement, then concrete installation, followed by pavement restoration and striping. Landscape restoration, planting, and installation of other amenities (where applicable) are the final items.

*Construction phasing and schedules are subject to change

Anticipated Impacts

Construction will impact adjacent residents and businesses, as well as the traveling public. The work will be phased to reduce those impacts where possible. Crews will work to maintain traffic whenever possible, however, you can expect traffic to be restricted to one-lane with flaggers at times.

Intermittent access closures may occur while utility or concrete work is underway. A safe walking route will be provided on one side of the block at a time.

Project Background and History

In 2019, the Moab City Council approved the Moab Parking Management Study to guide how parking concerns are addressed in the downtown area. Parking availability, relocation of parking following the recent U.S. 191 widening project, addressing the number of oversized vehicles and trailers, and safety considerations for vehicles, bicycles and pedestrians were all considered. In 2020, it was agreed that the Utah Department of Transportation (UDOT) recreation hotspot funding would be used to address congestion by dispersing parking around the downtown area to increase overall parking by 193 stalls.

In 2022, the City of Moab team held two workshops for area business owners, residents, and property owners, and a public open house to gather input on the proposed design. The final design has incorporated much of this public feedback to help address some issues and concerns the public shared with the team.

Moab has a Public Information Team for the Downtown Dispersed Parking Project. We are available to address questions or concerns specific to this project. Let us know how we can help!

Email: downtownparking@moabcity.org

Call: 888-670-0245

Discussions: All (1) Open (1)
  • Comments & Questions

    6 months ago
    Share Comments & Questions on Facebook Share Comments & Questions on Twitter Share Comments & Questions on Linkedin Email Comments & Questions link

    You need to be signed in to add your comment.

    Ask a question about this project, or share your comments or concerns with us here. You can also email or call the team at downtownparking@moabcity.org or 888-670-0254.

    Quick Reply
Page last updated: 19 Jul 2024, 07:29 AM