Kane Creek Boulevard Complete Streets Project

Share Kane Creek Boulevard Complete Streets Project on Facebook Share Kane Creek Boulevard Complete Streets Project on Twitter Share Kane Creek Boulevard Complete Streets Project on Linkedin Email Kane Creek Boulevard Complete Streets Project link

The City of Moab is redesigning Kane Creek Boulevard from Main Street to 500 West. Construction is scheduled to begin in mid-February 2024.

Project Update and Schedule

SCHEDULE: April 4 - April 18

The next two weeks work in ongoing to reconstruct underground utility features. New sewer lines have been being constructed for the past week and will continue for the near future. Additionally, crews are installing new manhole covers throughout the project. During this work large trenches will be open on the project and people who are walking through the project are encouraged to stay within designated areas behind fencing and traffic control.

Flagging operations will remain in effect. Please be aware of the direction of traffic and wait until you see cars moving in the direction you intend on traveling before entering the work zone. Expect delays of up to 15 minutes, and plan your journeys accordingly.

Project crews will be working 7:00 a.m. to 5:00 p.m. Monday through Friday. In order to optimize safety, travelers should remain aware of construction equipment, and obey all posted traffic control.

Three ways to stay current on the project:

  • Visit this project page, engagemoab.com/KaneCreek, frequently to see updates, and post questions and comments;
  • Sign up for email updates by emailing KaneCreek@moabcity.org;
  • Call the Public Involvement Team at 435-862-9216.
    *Schedule is subject to weather and other unforeseen circumstances.

KANE CREEK CONCEPT STREET DESIGN

Questions? Email KaneCreek@moabcity.org.


Kane Creek Boulevard Complete Streets Improvements Project Area
(The city's Kane Creek Boulevard improvements will affect only the section of road from Main Street to 500 West)Kane Creek Boulevard is one of the most heavily used streets in Moab, with 5,000 cars per day traveling between Main Street and 500 West where these improvements are planned. The complete streets design will better ensure safe access for motor vehicles, bicyclists, and pedestrians who rely on Kane Creek Boulevard daily. The complete streets approach not only considers vehicle traffic but also pedestrian and bicycle traffic to help ensure safe, comfortable access for all users.


Project Notice


The City of Moab is redesigning Kane Creek Boulevard from Main Street to 500 West. Construction is scheduled to begin in mid-February 2024.

Project Update and Schedule

SCHEDULE: April 4 - April 18

The next two weeks work in ongoing to reconstruct underground utility features. New sewer lines have been being constructed for the past week and will continue for the near future. Additionally, crews are installing new manhole covers throughout the project. During this work large trenches will be open on the project and people who are walking through the project are encouraged to stay within designated areas behind fencing and traffic control.

Flagging operations will remain in effect. Please be aware of the direction of traffic and wait until you see cars moving in the direction you intend on traveling before entering the work zone. Expect delays of up to 15 minutes, and plan your journeys accordingly.

Project crews will be working 7:00 a.m. to 5:00 p.m. Monday through Friday. In order to optimize safety, travelers should remain aware of construction equipment, and obey all posted traffic control.

Three ways to stay current on the project:

  • Visit this project page, engagemoab.com/KaneCreek, frequently to see updates, and post questions and comments;
  • Sign up for email updates by emailing KaneCreek@moabcity.org;
  • Call the Public Involvement Team at 435-862-9216.
    *Schedule is subject to weather and other unforeseen circumstances.

KANE CREEK CONCEPT STREET DESIGN

Questions? Email KaneCreek@moabcity.org.


Kane Creek Boulevard Complete Streets Improvements Project Area
(The city's Kane Creek Boulevard improvements will affect only the section of road from Main Street to 500 West)Kane Creek Boulevard is one of the most heavily used streets in Moab, with 5,000 cars per day traveling between Main Street and 500 West where these improvements are planned. The complete streets design will better ensure safe access for motor vehicles, bicyclists, and pedestrians who rely on Kane Creek Boulevard daily. The complete streets approach not only considers vehicle traffic but also pedestrian and bicycle traffic to help ensure safe, comfortable access for all users.


Project Notice


Comments & Questions

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share Who is the contractor to rebuild Kane Creek? on Facebook Share Who is the contractor to rebuild Kane Creek? on Twitter Share Who is the contractor to rebuild Kane Creek? on Linkedin Email Who is the contractor to rebuild Kane Creek? link

    Who is the contractor to rebuild Kane Creek?

    Kevin asked 3 months ago

    Thank you for your interest. The contractor for the project is Hank Williams Construction located in Norwood, CO. 

  • Share How can the general public see a breakdown of this project budget to see what parts are costing what percentages of the $8 million. I assumed most of the millions were for sewage for new low-income housing projects off the Kane Creek Apartments, with sewer lift station. But if some of this work will have to be torn up in the next 10 to 20 years to accomodate needed sewer lines, this is a waste of money. Also, if there are not utility stubs for known developements along this project...at least a break in the curb for access to the properties that have submitted plans...the lack of oversight and staying within budget...there is little accountability or logic. How can the general public respect the city needing millions of dollars for projects, when millions of dollars are wasted for aesthetics not needed by this population, while what is needed is basic improvement of infrastructure for utilities and development! on Facebook Share How can the general public see a breakdown of this project budget to see what parts are costing what percentages of the $8 million. I assumed most of the millions were for sewage for new low-income housing projects off the Kane Creek Apartments, with sewer lift station. But if some of this work will have to be torn up in the next 10 to 20 years to accomodate needed sewer lines, this is a waste of money. Also, if there are not utility stubs for known developements along this project...at least a break in the curb for access to the properties that have submitted plans...the lack of oversight and staying within budget...there is little accountability or logic. How can the general public respect the city needing millions of dollars for projects, when millions of dollars are wasted for aesthetics not needed by this population, while what is needed is basic improvement of infrastructure for utilities and development! on Twitter Share How can the general public see a breakdown of this project budget to see what parts are costing what percentages of the $8 million. I assumed most of the millions were for sewage for new low-income housing projects off the Kane Creek Apartments, with sewer lift station. But if some of this work will have to be torn up in the next 10 to 20 years to accomodate needed sewer lines, this is a waste of money. Also, if there are not utility stubs for known developements along this project...at least a break in the curb for access to the properties that have submitted plans...the lack of oversight and staying within budget...there is little accountability or logic. How can the general public respect the city needing millions of dollars for projects, when millions of dollars are wasted for aesthetics not needed by this population, while what is needed is basic improvement of infrastructure for utilities and development! on Linkedin Email How can the general public see a breakdown of this project budget to see what parts are costing what percentages of the $8 million. I assumed most of the millions were for sewage for new low-income housing projects off the Kane Creek Apartments, with sewer lift station. But if some of this work will have to be torn up in the next 10 to 20 years to accomodate needed sewer lines, this is a waste of money. Also, if there are not utility stubs for known developements along this project...at least a break in the curb for access to the properties that have submitted plans...the lack of oversight and staying within budget...there is little accountability or logic. How can the general public respect the city needing millions of dollars for projects, when millions of dollars are wasted for aesthetics not needed by this population, while what is needed is basic improvement of infrastructure for utilities and development! link

    How can the general public see a breakdown of this project budget to see what parts are costing what percentages of the $8 million. I assumed most of the millions were for sewage for new low-income housing projects off the Kane Creek Apartments, with sewer lift station. But if some of this work will have to be torn up in the next 10 to 20 years to accomodate needed sewer lines, this is a waste of money. Also, if there are not utility stubs for known developements along this project...at least a break in the curb for access to the properties that have submitted plans...the lack of oversight and staying within budget...there is little accountability or logic. How can the general public respect the city needing millions of dollars for projects, when millions of dollars are wasted for aesthetics not needed by this population, while what is needed is basic improvement of infrastructure for utilities and development!

    Molly Taylor asked 3 months ago

    Thanks for your comment! We are working on gathering this information for you. 

Page last updated: 08 Apr 2024, 08:15 AM